Project Start Date: Thu 7/1/04
Project Finish Date: Tue 4/5/05
ID | Task Name | Duration | Start | Finish | % Complete |
---|---|---|---|---|---|
1 | PreProduction | 21.33 days? | Thu 7/1/04 | Mon 7/26/04 | 77% |
2 | Setup and plan project | 0.44 days | Thu 7/1/04 | Thu 7/1/04 | 100% |
3 | Script 1st Draft | 1.69 days? | Thu 7/8/04 | Sat 7/10/04 | 100% |
4 | Storyboards | 8.06 days | Mon 7/12/04 | Tue 7/20/04 | 100% |
5 | 2D Animatic | 2 days | Tue 7/20/04 | Thu 7/22/04 | 0% |
6 | Character Designs | 7 days | Sat 7/10/04 | Mon 7/26/04 | 65% |
7 | Modeling | 19.55 days? | Mon 7/26/04 | Mon 8/23/04 | 6% |
8 | Model Characters | 12 days | Mon 7/26/04 | Sun 8/15/04 | 0% |
9 | Model "Stan" | 10 days | Mon 7/26/04 | Thu 8/5/04 | 0% |
10 | Model "Ollie" | 2 days | Thu 8/5/04 | Sun 8/15/04 | 0% |
11 | Model Environment | 4.55 days? | Sun 8/15/04 | Fri 8/20/04 | 25% |
12 | Room | 1 day | Sun 8/15/04 | Mon 8/16/04 | 0% |
13 | Tubes | 1 day? | Sun 8/15/04 | Mon 8/16/04 | 0% |
14 | Door | 1 day? | Sun 8/15/04 | Mon 8/16/04 | 0% |
15 | Light Fixture(s) | 1 day? | Thu 8/19/04 | Fri 8/20/04 | 100% |
16 | Model Props | 3 days? | Fri 8/20/04 | Mon 8/23/04 | 7% |
17 | Desk | 1 day? | Fri 8/20/04 | Sat 8/21/04 | 0% |
18 | Chair | 1 day? | Fri 8/20/04 | Sat 8/21/04 | 0% |
19 | Calculator | 1 day? | Fri 8/20/04 | Sat 8/21/04 | 0% |
20 | In/Out box | 1 day? | Fri 8/20/04 | Sat 8/21/04 | 0% |
21 | Wastepaper basket | 1 day? | Fri 8/20/04 | Sat 8/21/04 | 0% |
22 | Clock | 1 day? | Fri 8/20/04 | Sat 8/21/04 | 100% |
23 | Calendar | 1 day? | Fri 8/20/04 | Sat 8/21/04 | 0% |
24 | Employee Handbook | 1 day? | Fri 8/20/04 | Sat 8/21/04 | 0% |
25 | Forms | 1 day? | Fri 8/20/04 | Sat 8/21/04 | 0% |
26 | Pencil | 1 day? | Fri 8/20/04 | Sat 8/21/04 | 0% |
27 | Crumpled papers | 1 day? | Fri 8/20/04 | Sat 8/21/04 | 0% |
28 | Torn-off printouts | 1 day? | Fri 8/20/04 | Sat 8/21/04 | 0% |
29 | MODELING COMPLETE | 3 days | Fri 8/20/04 | Mon 8/23/04 | 0% |
30 | Rigging | 2 wks | Mon 8/23/04 | Tue 9/7/04 | 0% |
31 | Animation | 112.5 days | Tue 9/7/04 | Mon 2/28/05 | 0% |
32 | 2.5 minutes @ 6 hrs/sec | 900 hrs | Tue 9/7/04 | Mon 2/28/05 | 0% |
33 | Dynamics | 1 day? | Mon 2/28/05 | Tue 3/1/05 | 0% |
34 | Something to Remember | 1 day? | Mon 2/28/05 | Tue 3/1/05 | 0% |
35 | Texturing | 8 days? | Mon 2/28/05 | Wed 3/9/05 | 0% |
36 | Texture Characters | 3 days? | Mon 2/28/05 | Thu 3/3/05 | 0% |
37 | Texture Stan | 2 days | Mon 2/28/05 | Wed 3/2/05 | 0% |
38 | Texture Ollie | 1 day? | Wed 3/2/05 | Thu 3/3/05 | 0% |
39 | Texture Environment | 2 days? | Thu 3/3/05 | Sun 3/6/05 | 0% |
40 | Room | 2 days | Thu 3/3/05 | Sun 3/6/05 | 0% |
41 | Tubes | 1 day? | Thu 3/3/05 | Sat 3/5/05 | 0% |
42 | Door | 1 day? | Thu 3/3/05 | Sat 3/5/05 | 0% |
43 | Light Fixture(s) | 1 day? | Thu 3/3/05 | Sat 3/5/05 | 0% |
44 | Texture Props | 3 days? | Sun 3/6/05 | Wed 3/9/05 | 0% |
45 | Desk | 1 day? | Sun 3/6/05 | Mon 3/7/05 | 0% |
46 | Chair | 1 day? | Sun 3/6/05 | Mon 3/7/05 | 0% |
47 | Calculator | 1 day? | Sun 3/6/05 | Mon 3/7/05 | 0% |
48 | In/Out box | 1 day? | Sun 3/6/05 | Mon 3/7/05 | 0% |
49 | Wastepaper basket | 1 day? | Sun 3/6/05 | Mon 3/7/05 | 0% |
50 | Clock | 1 day? | Sun 3/6/05 | Mon 3/7/05 | 0% |
51 | Calendar | 1 day? | Sun 3/6/05 | Mon 3/7/05 | 0% |
52 | Employee Handbook | 1 day? | Sun 3/6/05 | Mon 3/7/05 | 0% |
53 | Forms | 1 day? | Sun 3/6/05 | Mon 3/7/05 | 0% |
54 | Pencil | 1 day? | Sun 3/6/05 | Mon 3/7/05 | 0% |
55 | Crumpled papers | 1 day? | Sun 3/6/05 | Mon 3/7/05 | 0% |
56 | Torn-off printouts | 1 day? | Sun 3/6/05 | Mon 3/7/05 | 0% |
57 | TEXTURING COMPLETE | 3 days | Sun 3/6/05 | Wed 3/9/05 | 0% |
58 | Lighting | 5 days | Wed 3/9/05 | Tue 3/15/05 | 0% |
59 | LIGHTING COMPLETE | 5 days | Wed 3/9/05 | Tue 3/15/05 | 0% |
60 | Rendering | 12.5 days | Tue 3/15/05 | Tue 3/29/05 | 0% |
61 | Render environment pass | 1 wk | Tue 3/15/05 | Tue 3/22/05 | 0% |
62 | Render animation pass | 2 wks | Tue 3/15/05 | Tue 3/29/05 | 0% |
63 | Render dynamics pass | 1 wk | Tue 3/15/05 | Tue 3/22/05 | 0% |
64 | Compositing | 2 days | Tue 3/29/05 | Thu 3/31/05 | 0% |
65 | Editing | 3 days | Thu 3/31/05 | Mon 4/4/05 | 0% |
66 | FINAL OUTPUT | 1 day? | Mon 4/4/05 | Tue 4/5/05 | 0% |